Implementation of Column Formwork Works on the 10th Floor in the Construction of Sky House Alam Sutera Phase 3 Building

Views icon

41

Views

Downloads icon

20

Downloads

Altmetrics icon

Altmetrics

Abstract

Formwork is a crucial component in reinforced concrete structural works. This study specifically discusses the application of aluminum formwork for column elements in high-rise buildings. Time inefficiency and quality issues encountered when using wooden or conventional formwork are major problems frequently found on construction sites. This study aims to identify the advantages and disadvantages of using aluminum formwork for columns and to evaluate its impact on construction time and the quality of the resulting product. The research employed a qualitative descriptive approach through direct observation and interviews with workers and project managers at the Sky House Alam Sutera Phase 3 building project. The results show that aluminum formwork can be installed and dismantled faster than wooden formwork, and it produces a smoother and more precise concrete surface. However, aluminum formwork has a higher initial procurement cost. Nevertheless, it is more cost-effective in the long term if properly maintained and reused multiple times. Due to its efficiency, neatness, and durability, aluminum formwork is a suitable choice for high-rise building projects.

References

  1. Aldy Kristian. (2024). Metode pelaksanaan pekerjaan struktur Fire Station MP 72. 22(87).
  2. American Concrete Institute. (2014). Guide to formwork for concrete (ACI 347R-14). ACI.
  3. Banua, J., Riogilang, H., & Rondonuwu, S. (2020). Metode pelaksanaan pekerjaan balok dan plat lantai dua pada pembangunan Mall Pelayanan Publik (MPP) Manado. Jurnal Sipil Statik, 8(6).
  4. Chitkara, K. K. (2014). Construction project management: Planning, scheduling and controlling. Tata McGraw-Hill.
  5. Clough, R. H., Sears, G. A., & Sears, S. K. (2015). Construction project management (6th ed.). Wiley.
  6. Fellows, R., & Liu, A. (2015). Research methods for construction (4th ed.). Wiley-Blackwell.
  7. Hanna, A. S. (1999). Concrete formwork systems. Journal of Construction Engineering and Management, 125(2), 102–110. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:2(102)
  8. Hinze, J. (2006). Construction safety. Prentice Hall.
  9. Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects. Construction Management and Economics, 15(1), 83–94. https://doi.org/10.1080/014461997373132
  10. Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.
  11. Kodek, J., & Vukomanović, M. (2018). Formwork systems and productivity in high-rise construction. Engineering, Construction and Architectural Management, 25(7), 865–881. https://doi.org/10.1108/ECAM-01-2017-0013
  12. Mosley, B., Bungey, J., & Hulse, R. (2012). Reinforced concrete design (7th ed.). Palgrave Macmillan.
  13. Nasikhin, M. K. (2023). Metode pelaksanaan pekerjaan struktur kolom pada proyek pembangunan Passenger Terminal Building Bandara Internasional Dhoho Kediri. Jurnal Vokasi Teknik Sipil, 1(3), 117–123.
  14. Neville, A. M., & Brooks, J. J. (2010). Concrete technology (2nd ed.). Pearson Education.
  15. Oglesby, C. H., Parker, H. W., & Howell, G. A. (1989). Productivity improvement in construction. McGraw-Hill.
  16. Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.). PMI.
  17. Shodiq, M. F., Setiawan, A., & Mayasari, I. (2024). Metode pelaksanaan pekerjaan konstruksi kolom dalam proyek pembangunan Masjid-BKMS JIIPE Gresik. DEARSIP: Journal of Architecture and Civil, 4(2), 58–71. https://doi.org/10.52166/dearsip.v4i02.7857
  18. Trijeti, & Hermawan, B. (2011). Studi perbandingan bekisting konvensional dengan PCH (Perth Construction Hire). Jurnal Konstruksia, 3(1), 45–55.

Author Biographies

How to Cite

Ghani Leo Frando, & Mulya, E. S. (2025). Implementation of Column Formwork Works on the 10th Floor in the Construction of Sky House Alam Sutera Phase 3 Building. Journal of Engineering and Science, 4(2), 67-77. https://doi.org/10.56347/jes.v4i2.309

Article Details

  • Volume: 4
  • Issue: 2
  • Pages: 67-77
  • Published:
  • Section: Articles
  • Copyright: 2025
  • ISSN: 2828-805X

License

Articles in this journal are published under the Creative Commons Attribution Licence (CC-BY 4.0). This means that users may share and adapt the articles published on this website in a reasonable manner, but they must give appropriate credit to the creator and indicate the changes they have made. Users must not apply additional restrictions, but must publish the work under the same license (CC-BY 4.0).

Similar Articles

Similar Articles

Discover other articles with topics similar to what you're currently reading. Find more references and expand your knowledge base.

Related Articles You May Be Interested In

More Similar Articles

Small-Scale Wind Power Generator with Inverse Taper and...

Rakhmad Syafutra Lubis, Teuku Muhayatsyah, Mahdi Syukri, Ramdhan Halid Siregar, Saifuddin Muhammad Jalil

Vol. 4 No. 1 (2025): June
Most read articles by the same author(s)

Related Articles